Please be aware that some works will be taking place in early 2025 to decommission part of the Esso Scott Freeman Gardens fuel pipeline. This pipeline is now redundant, as it has been replaced by the new Southampton to London pipeline project, which you may be familiar with.
What will happen?
The mechanics of the decommissioning work involves a combination of capping the old pipeline and filling it with ‘grout’, which is a cementitious powder mixed with water and then pumped into the pipeline, where it sets hard.
Where?
One of the sites is Scott Freeman Gardens in Ashford, which is owned by Spelthorne Borough Council (SBC)

When?
The works are due to start on 7th January 2025 and are targeted to complete in two weeks. To help the contractor carry out works safely they will be creating a temporary compound area within Scott Freeman Gardens and will require traffic management to be in place on Stanwell Road at certain times during the works.
The decommissioning programme is currently running to schedule, but if there are any changes we will update you as soon as we are made aware.
Michelle Arnold
Ashford Town Ward Councillor
cllr.arnold@spelthorne.gov.uk

Catch Up On Other News
Stay up to date with the latest from Independent Spelthorne Group
-
Emergency Works
Emergency Works Scottish & Southern Electricity Networks on Staines Road West Cadent Gas on Stanwell Road, Ashford outside no.151
-
Highways Tree Felling Map
➡️Link to Highways Tree Felling Map here⬅️ ** Repost from Surrey Highways ** There are approximately 2 million trees growing on Surrey’s highway network. They…
-
Household Support Fund, Summer 2024
**** Repost from https://www.spelthorne.gov.uk/householdsupport Spelthorne Borough Council has opened an application window for NEW claimants of the Household Support Fund as part of Spelthorne Borough Council’s…
-
Longdan Supermarket, Staines High Street
Longdan supermarket in Staines High Street has applied for a licence to sell alcohol until 22:00 under the Licensing Act 2003. This application (and the…